Northern New York Newspapers
Watertown
Ogdensburg
Massena-Potsdam
Lowville
Carthage
Malone
NNY Business
NNY Living
NNY Ads
Wed., Dec. 17
ADVERTISE SUBSCRIBE
Serving the communities of Jefferson, St. Lawrence and Lewis counties, New York
In print daily. Online always.

Governor announces work on four Jefferson County bridges to the tune of $5.9 million

PREV
NEXT
ARTICLE OPTIONS
A A
print this article
e-mail this article

Gov. Andrew M. Cuomo announced Thursday that the state will spend $5.9 million to repair the underlying steel structures and replace critical components of four bridges in Jefferson County.

The bridges are:

n The Route 971V bridge carrying the access road from Route 3 to Fort Drum over the Black River in the town of LeRay. The bridge is closed during construction and traffic is detoured along routes 3 and 342. Work on the $2.1 million project is expected to be completed by the fall.

n Route 177 over the north branch of Sandy Creek in the town of Rodman. The bridge will remain in service during construction using a temporary traffic signal. Work on this $2.3 million project is expected to be completed by late fall.

n Route 193 bridges over Interstate 81 northbound and southbound in the town of Ellisburg. The bridges will be closed during construction and the detour will use other interstate exits. Work on the $1.5 million project is expected to begin in May and be completed by late fall.

Commenting rules:
  1. Stick to the topic of the article/letter/editorial.
  2. When responding to issues raised by other commenters, do not engage in personal attacks or name-calling.
  3. Comments that include profanity/obscenities or are libelous in nature will be removed without warning.
Violators' commenting privileges may be revoked indefinitely. By commenting you agree to our full Terms of Use.
Giveaway
Syracuse Football Tickets Giveaway
Connect with Us
WDT News FeedsWDT on FacebookWDT on TwitterWDT on InstagramWDT for iOS: iPad, iPhone, and iPod touchWDT for Android
Showcase of Homes
Showcase of Homes